Westown Construction

First 2 Concrete Slabs For Westown

Over the last 2 weeks, the Stefanutti Stocks team has laid the first 2 concrete slabs for Westown Square.
The first was laid on Saturday 19th August, where an impressive 519m³ of concrete was poured and the second was on Wednesday 31st August where a massive 600m³ of concrete was poured under the light of the Super Blue Moon.

See more pics of construction progress on the Westown website 

First 2 Concrete Slabs For Westown Square (4) First 2 Concrete Slabs For Westown Square (4)